HFHSC Weekly Construction Report 5/9/16

Posted on Posted in Construction

The Habitat for Humanities of Snohomish Co. (HFHSC) weekly construction report keeps stakeholders informed and involved. Published Mondays. Covers our active projects. Feedback/questions welcome at construction@habitatsnohomish.org.

Highlights
– P2 permits ready for pick-up as of 5/13/16
– P2 project kickoff 6p 5/17/16 at office
– P2 first build day 5/18/16 – begins Step 2

Phoenix 2 (P2) Received notice permits are ready to pick-up. More detail here.

On Tuesday 5/17/16 the construction mgmt team gets together for Phoenix 2 construction kick-off. A chance to discussion overall expectations and objectives for project. Overall, we want to deliver a great Habitat builder experience on the way to delivering P2 mid-December. Now that Step 1 Plan Permits is complete see “What’s after P2 permits?

Twin Creeks (TC) No significant TC activities this week. Did not get carpet stretched as planned (2nd week); bumps to coming week. See more on TC work item list. Five of seven units occupied. One ready to occupy. Target 100% occupancy on 7/1/16. (TC site map)

Everett Store Fence Underground utility survey complete. No conflicts with pole layout. See work item list. Will complete work items alongside P2 effort keeping in mind our end-date 6/17/16.

Altena Gardens Project complete.

Construction Calendar (link opens new window)
Construction Calendar Revised 05 16 16

Changes since last week: none

Weekly Construction Report Index – All reports starting 11/1/15.

Come help us build stuff!

Chris Anderson, Construction Manager
Habitat for Humanities of Snohomish Co. (HFHSC)