by Chris | Jun 29, 2018 | Construction
As we prepare to clear the Twin Creeks Village site of existing structures, I learned the Everett FD might value our structures as a training site. A quick email to Jim Venturo, the Assistant Chief who reviews our building plans, connected me to Ric Cade, Assistant...
by Chris | Jun 22, 2018 | Construction, Report
Highlights include: All complete except for the critical water line connection work by the water dept. First of six final inspections, passes with no corrections. The TCV planning effort breaks into three pieces – demo structures, get permit for require fill...
by Chris | Jun 22, 2018 | Construction, Report
Highlights: Phase 1, the Jimenez Family home, nears completion. Only a few critical items remain undone. A regular on-site builder starts forecasting costs for subdivision’s civil engineering activities and costs. Gold Bar 2 Step 1 Planning and Permit costs go...
by Chris | Jun 22, 2018 | Construction, Report
Late posting…HFHSC Construction Manager Report for FY18 Month 9 MAR Key items: Phase 1 project moves into Step 5 Interior Trim-out. The long and last of the five steps. TCV Master Plan subdivision application readied for submission and formal review. We...
by Chris | Jun 22, 2018 | Construction, Report
Just submitted this report to construction cmte and Roger. And now to you. This is the final month in the planning year for the affiliate. Good results this year in the construction dept. But a significant increase in doing – getting more done – required...