fbpx

Gold Bar 2 Construction Update 7/24/19

We had a productive and quiet day on-site Wednesday, August 24th. Primary activity was installing peel-and-stick Vycor house wrap, a donation from Grace Building Products. After a little practice the house wrap team was delivering good clean sheets with on-target...

Gold Bar 2 Construction Update 8/30/19

  Solid effort over the last several weeks are bringing us to the conclusion of Step 3 – Structure/Dry-in, and at the same time completing activities required in Step 4 – Systems/Rough-in. During the August 17 Saturday build Builder’s Club...
Build Report – Gold Bar 2 – 8/16/19

Build Report – Gold Bar 2 – 8/16/19

Another day of solid progress on the Gold Bar 2 site! Twelve builders donated close to one hundred hours, pushing forward in a number of areas: Shiner Patrol took a final pass on roof nailing and found a few shiners which we pulled and re-nailed. We also, after...
Gold Bar 2 Construction Update 8/7/19

Gold Bar 2 Construction Update 8/7/19

Many thanks, builders, for a productive week at Gold Bar 2. Twelve builders started Wednesday morning, July 31. The house wrap team got started while others helped get trusses lifted into place and ready for installation. By lunch time the house wrap crew had...

Thanks to WCC Builders!

A big thank you to a crew of builders from the Washington Conservation Corps. The five builders, normally working to restore Snohomish Co. wetlands and rivers, chose Monday to serve Habitat Families. They built some important display fixtures for the Smokey Point...

Gold Bar 2 – first (informal) build

Needed to get a fence up across the Gold Bar property on Saturday 8/4. Some campers reportedly using our land to access May Creek (on the W prop line). Also met more neighbors in the immediate neighborhood. Warm welcome as we plan to build on the last undeveloped lot...