We’ve met a major milestone with our current project, Twin Creeks Village Phase 1. Last week we earned our rough-in inspections for electrical, plumbing, and mechanical systems, and a building inspection. All four city inspections are required before insulation installation can begin. With the win last week we installed all insulation (except attic) today (Mon 1/30). Early tomorrow our drywall will be delivered. On Wednesday the crew starts installing drywall. We expect to be installing drywall for about five build days.

Here’s the progress board for Phase 1.

With the completion of drywall installation, and drywall taping and finishing later this month, we’ll be through Step 4 and on our way into the final step of construction, #5 Interior and Trim-out.

Many thanks to all the builders who’ve carried this far!

Chris