by Steven Li | Oct 23, 2019 | Construction
We met our goal for last week: applying interior wall texture and priming all drywall surfaces. So many to thank! Earlier this month, we benefited from a special contribution from Interior Finishing Trades NW, a commercial finish trade school. Eric Palmer held his...
by Steven Li | Aug 30, 2019 | Construction
Solid effort over the last several weeks are bringing us to the conclusion of Step 3 – Structure/Dry-in, and at the same time completing activities required in Step 4 – Systems/Rough-in. During the August 17 Saturday build Builder’s Club regulars...
by Steven Li | Aug 16, 2019 | Construction
Another day of solid progress on the Gold Bar 2 site! Twelve builders donated close to one hundred hours, pushing forward in a number of areas: Shiner Patrol took a final pass on roof nailing and found a few shiners which we pulled and re-nailed. We also, after...
by Steven Li | Aug 7, 2019 | Construction
Many thanks, builders, for a productive week at Gold Bar 2. Twelve builders started Wednesday morning, July 31. The house wrap team got started while others helped get trusses lifted into place and ready for installation. By lunch time the house wrap crew had...
by Steven Li | Jul 26, 2019 | Construction
We had a productive and quiet day on-site Wednesday, August 24th. Primary activity was installing peel-and-stick Vycor house wrap, a donation from Grace Building Products. After a little practice the house wrap team was delivering good clean sheets with on-target...